Construction Schedule update for Village of Saranac Lake Projects:

Week of September 24th thru September 28th: Removal of Sidewalk and Curb on Academy Street.  Installation of Curb and Sidewalk on Sheppard Street.  Water line work on Sheppard Avenue and Front Street on Wednesday September 26th (Expect a disruption of water service for duration of the day).  Milling of Canaras Street and Park Avenue (Circle Street to Old Military Road) Thursday September 27th and Helen Street and Pine Street September 28th.  Streets will be closed to all traffic with the exception of bus traffic  on the days indicated as well as all parking will be prohibited on these streets from 6:30 A.M. until 6:00 P.M.

Week of October 1st thru October 5th:  Milling of Sheppard Avenue and Clinton Street from Franklin to Sheppard Avenue Monday October 1st.  Streets will be closed to all traffic with the exception of bus traffic  on the days indicated as well as all parking will be prohibited on these streets from 6:30 A.M. until 6:00 P.M.   Sidewalk and curb installation will also be done on Academy Street for the duration of the week.   Village forces will also be performing all cleanup and paving preparation on the milled streets immediately after milling.

Week of October 9th through October 16th: Paving operations on Canaras Street, Park Avenue, Sheppard Avenue, State Street, Helen Street, Pine Street and Clinton Streets.  All streets will be closed to ALL traffic on the day of paving.

 

 