Work on Duprey Street Begins Monday

SARANAC LAKE: The Duprey Street Sewer Main Replacement Project is set to commence on Monday    Duprey street will be closed to all thru traffic between Lake Flower Avenue and Tara Drive.  Traffic will be detoured onto Edwards Street and then Tara Drive.    Only those locals who live on or are conducting business on Duprey Street between Tara Drive and LakeFlower will be allowed to access the site.  Traffic will be reduced to one lane traffic at night and will be restored to two way traffic on the weekend.   The road closure will be between the hours of 7:00 am until 4:00 pm.  A copy of the construction schedule is as follows:

TENTATIVE DUPREY ST CONSTRUCTION SCHEDULE

This week – week of 5/28 – 5/30 – JE Sheehan will be mobilizing additional equipment to the Village including bypass pumps

Next week – week of 6/2-6/6 – JE Sheehan will be installing manholes, sewer main and sewer laterals starting at the manhole closest to Route 86

Week of 6/9-6/13 – JE Sheehan will continue installing manholes, sewer main and sewer laterals

Week of 6/16-6/20 – JE Sheehan will be reconstructing the road with new fabric gravel and asphalt

Week of 6/23-6/27 – JE Sheehan will complete any final restorations, topsoil, seeding and removal of equipment